School bond passed, work begins

Nicole Frey
Preston Utley/Vail DailyLouise Funk and supporters of passing a school bond to pay for a new high school and other improvements rallied at Edwards Elementary School Tuesday.
ALL |

EAGLE – Now that Eagle County’s School’s $128 million bond has passed, school staff and board members are realizing the work has just begun. “We just had one of the biggest successes in the district,” Superintendent John Brendza said. “It proves that the community does support our schools. We just created an awful lot of work for ourselves.”Not only did the county vote for the school bond, the state defeated an amendment and referendum that would have put restrictions on how schools spend money. “All of the things that could have had a negative impact on us went down and everything that could have impacted us positively went up,” said Assistant Superintendent Karen Strakbein. “It’s was a very good night for us. The campaign committee did a phenomenal job for us.”Approval of the bond, which will go toward building new schools, including a new high school where Berry Creek Equestrian Center now stands, and updating existing ones, doesn’t mean the school district gets a $128 million check to play with. It’s a little more complicated than that. After wading through the legal paperwork, the district hopes to start selling bonds in early January. “It is better to plan well and come out of planning a little late than to rush through planning,” Strakbein said. Strakbein recommended the district ask Architectural Resource Consultants to act as the owner’s representative – someone hired by the district to make sure projects are done on time and on budget – on the construction of the new high school and new elementary school, the remolding of Eagle Valley High School and other repairs and upgrades, including Battle Mountain High School. If Architectural Resource Consultants’ price isn’t right, then Strakbein recommended soliciting other bids, but she wants the process done by Dec. 1. Also to be completed by Dec. 1, Strakbein also told the school board she’d like to get a price estimate from Ennovate Corporations to act as the project manager on energy-saving upgrades around the district, like energy-efficient boilers. The board has until Jan. 1 to figure out if they want a construction manager and hire one. Strakbein also advised the board to choose an architect for the projects by Dec. 31. As everyone gets to work, there are still a few outstanding issues – relocating Red Canyon High School, because the new elementary school will be built on Red Canyon’s east campus and what to do about a transportation center. “We just can’t wait to start implementing,” Strakbein said.

New high school• November to December – select architect• November – select surveying, geotech and environmental firms• December – conduct surveying, geotech and environmental analysis• January to December 2007 – design of building, site visits, host design advisory group

• January 2008 – award construction contract • January 2009 to Aug. 2009 – construction • July to August 2009 -move in• August or September 2009 – building ready for useNew elementary school• November to December – select architect• November – select surveying, geotech and environmental firms• December – conduct surveying, geotech and environmental analysis• January to May 2007 – design of building, site visits, host design advisory group• May 2007 – award construction contract • May 2007 to May 2008 – construction

• May to July 2008 – move in• August or September 2009 – building ready for useRemodel Eagle Valley High School• November to December 2006 – select architect• January to May 2007 – design of building renovation, host design advisory group• May 2007 – Award construction contract• June 2007 to January 2008 – construction• December 2007 to January 2008 – move in • February 2008 – area ready for useRenovate Battle Mountain High School

• November to December 2006 – select architect• August 2008 to May 2009 – design of building renovation, host design advisory group• May 2009 – award construction contract• May to November 2009 – construction• November to December 2009 – move in• January 2010 – building ready for useFacility repair projects• November to December 2006 – select architect• January to February 2007 – design of building renovation, host design advisory group• March to May 2007 – award construction contracts• May to November 2007 – construction • August to December 2007 – repair projects completeStaff Writer Nicole Frey can be reached at 949-0555, ext. 14621, or nfrey@vaildaily.com.Vail, Colorado